Due to improvements being made around the school, the building will be closed to all employees for a portion of the summer. Please see the important dates below to see how this may impact you and your summer plans. Please make all necessary arrangements as there can be no exceptions to these dates and no access during these times.
Important Dates
- May 28, 2019 – Begin demolition in the Main Gym and both balconies. The demolition team will work from 3 to 11 p.m. each evening.
- June 10, 2019 – July 7, 2019– Building closed to all staff for Tile replacement and additional work in the Main Gym and Field House.
- July 8, 2019 – Staff may return to the main office area and selected first floor areas. Second floor areas, Main Gym, and Field House still closed.
- August 5, 2019 – Building access to first and second floor areas. Main gym and Field House still closed.
- August 14, 2019 – Full building access including Main Gym and Field House.